A can complete a job in 20 days. A works for 5 days and leaves; B finishes the rest in 12 days. B alone can complete the whole job in:
About this question
- Exam:
- TSPSC Group 4
- Topic:
- Arithmetic · Time and work
More questions on this topic
- 9 persons complete a work in 20 days. How many persons are needed to finish it in 12 days (same rate)?
- 10 clerks copy a register in 24 days. To finish in 15 days, clerks needed (same pace) are:
- Pipe A fills a tank in 12 hours and pipe B empties it in 16 hours. If both are opened together, the tank fill…
- A and B work in the efficiency ratio 3 : 2. Together they finish a job in 20 days. A alone will finish it in:
- A finishes a job in 12 days and B in 18 days. Working together they finish in:
About this practice question
This is a free PrajaPrep practice question for TSPSC Group 4. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- 9 persons complete a work in 20 days. How many persons are needed to finish it in 12 days (same rate)?
- 10 clerks copy a register in 24 days. To finish in 15 days, clerks needed (same pace) are:
- Pipe A fills a tank in 12 hours and pipe B empties it in 16 hours. If both are opened together, the tank fills in:
- A and B work in the efficiency ratio 3 : 2. Together they finish a job in 20 days. A alone will finish it in:
- A finishes a job in 12 days and B in 18 days. Working together they finish in:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
A does 5/20 = 1/4; remaining 3/4 takes B 12 days → B alone = 12 × 4/3 = 16 days.