A and B work in the efficiency ratio 3 : 2. Together they finish a job in 20 days. A alone will finish it in:
About this question
- Exam:
- TSPSC Group 4
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A finishes a job in 12 days and B in 18 days. Working together they finish in:
- 12 masons finish a wall in 20 days. At the same pace, 16 masons need:
- A finishes a work in 16 days and B in 21 days. Together they take:
- A can finish a work in 10 days and B in 15 days. Working together, they can finish it in:
- 12 workers finish a job in 18 days. 8 workers, at the same rate, will take:
About this practice question
This is a free PrajaPrep practice question for TSPSC Group 4. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A finishes a job in 12 days and B in 18 days. Working together they finish in:
- 12 masons finish a wall in 20 days. At the same pace, 16 masons need:
- A finishes a work in 16 days and B in 21 days. Together they take:
- A can finish a work in 10 days and B in 15 days. Working together, they can finish it in:
- 12 workers finish a job in 18 days. 8 workers, at the same rate, will take:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Combined 5 parts = 1/20 per day; A's 3 parts → A alone = 20 × 5/3 = 100/3 days.