9 persons complete a work in 20 days. How many persons are needed to finish it in 12 days (same rate)?
About this question
- Exam:
- TSPSC Group 4
- Topic:
- Arithmetic · Time and work
More questions on this topic
- 10 clerks copy a register in 24 days. To finish in 15 days, clerks needed (same pace) are:
- Pipe A fills a tank in 12 hours and pipe B empties it in 16 hours. If both are opened together, the tank fill…
- A and B work in the efficiency ratio 3 : 2. Together they finish a job in 20 days. A alone will finish it in:
- A finishes a job in 12 days and B in 18 days. Working together they finish in:
- 12 masons finish a wall in 20 days. At the same pace, 16 masons need:
About this practice question
This is a free PrajaPrep practice question for TSPSC Group 4. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- 10 clerks copy a register in 24 days. To finish in 15 days, clerks needed (same pace) are:
- Pipe A fills a tank in 12 hours and pipe B empties it in 16 hours. If both are opened together, the tank fills in:
- A and B work in the efficiency ratio 3 : 2. Together they finish a job in 20 days. A alone will finish it in:
- A finishes a job in 12 days and B in 18 days. Working together they finish in:
- 12 masons finish a wall in 20 days. At the same pace, 16 masons need:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
The work needs 9 × 20 = 180 person-days. To finish in 12 days you need 180 ÷ 12 = 15 persons.