A alone can do a piece of work in 10 days and B alone can do the same work in 15 days. A and B agreed to complete the work for ₹30,000. With the help of C, they completed the work in 5 days. Then the amount to be paid to C is
About this question
- Exam:
- Telangana SI (TSLPRB)
- Topic:
- Arithmetic · Time and work
More questions on this topic
- The wages of 3 boys are equal to the wages of 2 men. The amount of work done by 3 men is equal to the amount…
- Three persons A, B and C can do a piece of work in 18, 36 and 48 days respectively. A, B and C together start…
- Two inlet pipes A and B working together for 4 hours fill 72 units of water in a tank having capacity 160 uni…
- A can complete a piece of work in 18 days and B can complete the same work in 12 days. Both begin the work to…
- Pipe A alone can fill a tank in 24 minutes. Pipe B alone can fill the same tank in 36 minutes. Pipe A alone i…
About this practice question
This is a free PrajaPrep practice question for Telangana SI (TSLPRB). It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- The wages of 3 boys are equal to the wages of 2 men. The amount of work done by 3 men is equal to the amount of work done by 5 boys. If 40 boys and 15 men worked for 8 weeks to complete a work and the total wages they got are equal to Rs.12,600 then the wages 20 boys and 20 men get to complete that work is (in rupees)
- Three persons A, B and C can do a piece of work in 18, 36 and 48 days respectively. A, B and C together start working. After 3 days, A leaves the job and B and C continue the job, but due to some reason B also leaves the job after 3 days, whereas C continues till the end of the job. I. A and B together can finish the job in 12 days. II. After the departure of A and B, C alone finishes the job in 26 more days. Which of the following options is correct ?
- Two inlet pipes A and B working together for 4 hours fill 72 units of water in a tank having capacity 160 units. If A alone can fill the tank in 20 hours, the time taken by B alone to fill the tank is
- A can complete a piece of work in 18 days and B can complete the same work in 12 days. Both begin the work together but after some days, B leaves the work. If A finishes the remaining work in 3 days, then the number of days B worked is
- Pipe A alone can fill a tank in 24 minutes. Pipe B alone can fill the same tank in 36 minutes. Pipe A alone is opened for x minutes and Pipe B alone is opened for y minutes to fill the tank in 30 minutes. Then |x - y| = (in minutes)
Answer and explanation
If you want to check after trying the question, the short explanation is here.
In 5 days A does 1/2, B does 1/3, so C does 1/6. Pay follows work: C's share (1/6) is 1/3 of A's (1/2).