Tap an option below to check the answer and explanation.
The wages of 3 boys are equal to the wages of 2 men. The amount of work done by 3 men is equal to the amount of work done by 5 boys. If 40 boys and 15 men worked for 8 weeks to complete a work and the total wages they got are equal to Rs.12,600 then the wages 20 boys and 20 men get to complete that work is (in rupees)
About this question
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Two inlet pipes A and B working together for 4 hours fill 72 units of water in a tank having capacity 160 uni…
- A can complete a piece of work in 18 days and B can complete the same work in 12 days. Both begin the work to…
- Pipe A alone can fill a tank in 24 minutes. Pipe B alone can fill the same tank in 36 minutes. Pipe A alone i…
- Pipe A can fill a tank in 30 minutes and Pipe B can fill it in 45 minutes. But third Pipe C can empty a full…
- Three persons X, Y and Z are employed to do a piece of work. X and Y together completed 21/25 part of the wor…
About this practice question
This is a free PrajaPrep practice question for Telangana Constable (TSLPRB). It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Two inlet pipes A and B working together for 4 hours fill 72 units of water in a tank having capacity 160 units. If A alone can fill the tank in 20 hours, the time taken by B alone to fill the tank is
- A can complete a piece of work in 18 days and B can complete the same work in 12 days. Both begin the work together but after some days, B leaves the work. If A finishes the remaining work in 3 days, then the number of days B worked is
- Pipe A alone can fill a tank in 24 minutes. Pipe B alone can fill the same tank in 36 minutes. Pipe A alone is opened for x minutes and Pipe B alone is opened for y minutes to fill the tank in 30 minutes. Then |x - y| = (in minutes)
- Pipe A can fill a tank in 30 minutes and Pipe B can fill it in 45 minutes. But third Pipe C can empty a full tank in 15 minutes. A and B are kept open for 15 minutes in the beginning and then C is also opened. Since then the time required (in minutes) to empty the tank is
- Three persons X, Y and Z are employed to do a piece of work. X and Y together completed 21/25 part of the work. Y and Z together completed 8/25 part of the work. If all the 3 agreed to complete the work for ₹3,250, then the amount X receives more than that of Z is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
In boy units, a man does 5/3 of the work and earns 1.5 times. Work = (40 + 25) × 8 = 520 boy-weeks. Weekly wage of one boy = 12,600 ÷ (62.5 × 8) = 25.2. The new team does 53⅓ boy-units a week, so it takes 9.75 weeks. Its wage = 50 × 25.2 × 9.75 = 12,285.