A finishes a work in 13 days and B in 21 days. Together they take:
About this question
- Exam:
- TG Office Subordinate
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipe A fills a tank in 15 hours and pipe B in 10 hours. Together they fill it in:
- A alone can complete a job in 16 days. After working 4 days, A leaves and B finishes the remaining work in 18…
- A and B together finish a work in 18 days. A alone takes 30 days. B alone takes:
- A can finish a job in 10 days, B in 15 days. Working together they take:
- A can complete a job in 20 days. A works for 5 days and leaves; B finishes the rest in 12 days. B alone can c…
About this practice question
This is a free PrajaPrep practice question for TG Office Subordinate. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipe A fills a tank in 15 hours and pipe B in 10 hours. Together they fill it in:
- A alone can complete a job in 16 days. After working 4 days, A leaves and B finishes the remaining work in 18 days. B alone can do the whole work in:
- A and B together finish a work in 18 days. A alone takes 30 days. B alone takes:
- A can finish a job in 10 days, B in 15 days. Working together they take:
- A can complete a job in 20 days. A works for 5 days and leaves; B finishes the rest in 12 days. B alone can complete the whole job in:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
A does 1/13 of the work a day and B does 1/21. Together: 1/13 + 1/21 = 34/273 a day, so they need 273 ÷ 34 ≈ 8.03 days. Together must be faster than A alone, so anything above 13 days is wrong.