24 workers finish a job in 18 days. How many days will 16 workers take at the same rate?
About this question
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A finishes a work in 13 days and B in 21 days. Together they take:
- Pipe A fills a tank in 15 hours and pipe B in 10 hours. Together they fill it in:
- A alone can complete a job in 16 days. After working 4 days, A leaves and B finishes the remaining work in 18…
- A and B together finish a work in 18 days. A alone takes 30 days. B alone takes:
- A can finish a job in 10 days, B in 15 days. Working together they take:
About this practice question
This is a free PrajaPrep practice question for SSC CPO (SI CAPF / Delhi Police). It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A finishes a work in 13 days and B in 21 days. Together they take:
- Pipe A fills a tank in 15 hours and pipe B in 10 hours. Together they fill it in:
- A alone can complete a job in 16 days. After working 4 days, A leaves and B finishes the remaining work in 18 days. B alone can do the whole work in:
- A and B together finish a work in 18 days. A alone takes 30 days. B alone takes:
- A can finish a job in 10 days, B in 15 days. Working together they take:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Work = 24 × 18 = 432 worker-days. Days = 432/16 = 27.