Tap an option below to check the answer and explanation.
A does a job in 6 days, B in 12 days. Together they take:
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- 10 workers finish in 12 days. 15 workers take:
- 12 workers can complete a job in 18 days. How many days will 9 workers take for the same job (same rate)?
- 15 labourers finish a task in 16 days. How many days will 20 labourers need at the same rate?
- A tap fills a tank in 8 hours and a leak empties it in 12 hours. If both are open, the tank fills in:
- A finishes a work in 17 days and B in 21 days. Together they take:
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- 10 workers finish in 12 days. 15 workers take:
- 12 workers can complete a job in 18 days. How many days will 9 workers take for the same job (same rate)?
- 15 labourers finish a task in 16 days. How many days will 20 labourers need at the same rate?
- A tap fills a tank in 8 hours and a leak empties it in 12 hours. If both are open, the tank fills in:
- A finishes a work in 17 days and B in 21 days. Together they take:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
A does 1/6 a day and B 1/12. Together: 1/6 + 1/12 = 2/12 + 1/12 = 3/12 = 1/4, so 4 days. Averaging the two times (9 days) is the trap.