15 labourers finish a task in 16 days. How many days will 20 labourers need at the same rate?
About this question
- Exam:
- TSPSC Group 4
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A tap fills a tank in 8 hours and a leak empties it in 12 hours. If both are open, the tank fills in:
- A finishes a work in 17 days and B in 21 days. Together they take:
- A finishes in 8 days. In 2 days A does:
- Kiran and Latha together take 16 days. Kiran alone takes 24 days. Latha alone takes:
- 16 women can complete a work in 24 days. How many days will 12 women take (same rate)?
About this practice question
This is a free PrajaPrep practice question for TSPSC Group 4. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A tap fills a tank in 8 hours and a leak empties it in 12 hours. If both are open, the tank fills in:
- A finishes a work in 17 days and B in 21 days. Together they take:
- A finishes in 8 days. In 2 days A does:
- Kiran and Latha together take 16 days. Kiran alone takes 24 days. Latha alone takes:
- 16 women can complete a work in 24 days. How many days will 12 women take (same rate)?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Person-days = 15 × 16 = 240. Days = 240/20 = 12.