A finishes a job in 8 days and B finishes it in 24 days. Together they take:
About this question
- Exam:
- TSPSC Group 4
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Tap P fills a cistern in 10 hours and tap Q fills it in 15 hours. Both together fill it in:
- A tap fills a tank in 8 hours. In 3 hours it fills:
- A and B together can finish a work in 10 days. A alone can do it in 15 days. B alone can do it in:
- A does a job in 6 days, B in 12 days. Together they take:
- 10 workers finish in 12 days. 15 workers take:
About this practice question
This is a free PrajaPrep practice question for TSPSC Group 4. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Tap P fills a cistern in 10 hours and tap Q fills it in 15 hours. Both together fill it in:
- A tap fills a tank in 8 hours. In 3 hours it fills:
- A and B together can finish a work in 10 days. A alone can do it in 15 days. B alone can do it in:
- A does a job in 6 days, B in 12 days. Together they take:
- 10 workers finish in 12 days. 15 workers take:
Answer and explanation
If you want to check after trying the question, the short explanation is here.
A does 1/8 a day and B 1/24. Together: 1/8 + 1/24 = 3/24 + 1/24 = 4/24 = 1/6, so 6 days. It must be less than A's 8 days.