If 8 men can do a piece of work in 14 days, the time taken by 12 men to do the same piece of work will be:
About this question
- Exam:
- SSC CHSL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A can paint a painting in 12 days. B can paint the same in 8 days. C can paint the same in 10 days. Find the…
- Arvind works 4 times as fast as Suresh. If Suresh can complete a work in 20 days independently, then find the…
- A pipe can fill a cistern in 8 hours. Due to a leak at the bottom, it is filled in 10 hours. In how many hour…
- Pipe A can fill a tank in 4 hours, pipe B can fill the same tank in 6 hours and pipe C can fill the same tank…
- Three printing machines, P, Q and R, when each is working alone, can print one lakh books in, respectively, 8…
About this practice question
This is a free PrajaPrep practice question for SSC CHSL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A can paint a painting in 12 days. B can paint the same in 8 days. C can paint the same in 10 days. Find the (approximate) number of days in which the painting can be painted by A if he is accompanied by both B and C together on alternate days and A starts painting on the first day alone.
- Arvind works 4 times as fast as Suresh. If Suresh can complete a work in 20 days independently, then find the number of days in which Arvind and Suresh can together finish the work.
- A pipe can fill a cistern in 8 hours. Due to a leak at the bottom, it is filled in 10 hours. In how many hours can the leak alone empty the full cistern?
- Pipe A can fill a tank in 4 hours, pipe B can fill the same tank in 6 hours and pipe C can fill the same tank in 12 hours. The time taken (in hours) by them to fill half of the same tank if they operate together is:
- Three printing machines, P, Q and R, when each is working alone, can print one lakh books in, respectively, 8 hours, 16 hours and 24 hours. These machines print books in turns of one hour each, starting with P, followed by Q and then by R. However, after a total of 9 hours, P stops functioning, but Q and R continue working alternately for an hour each, with Q working during the 10th hour, till the printing of all the one lakh books is completed. In how many hours in all did machines Q and R complete printing the remaining books?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
The work is 8 × 14 = 112 man-days, so 12 men need 112/12 = 9⅓ days, about 9.33 days.