Three printing machines, P, Q and R, when each is working alone, can print one lakh books in, respectively, 8 hours, 16 hours and 24 hours. These machines print books in turns of one hour each, starting with P, followed by Q and then by R. However, after a total of 9 hours, P stops functioning, but Q and R continue working alternately for an hour each, with Q working during the 10th hour, till the printing of all the one lakh books is completed. In how many hours in all did machines Q and R complete printing the remaining books?
About this question
- Exam:
- RRB NTPC Graduate
- Topic:
- Arithmetic · Time and work
More questions on this topic
- If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same wo…
- When A alone does a piece of work, he takes 25 days more than the time taken by A and B to do the work togeth…
- A is able to complete a task in 15 days, while B takes 20 days to finish the same task. If they collaborate a…
- Pipes X, Y, and Z together can fill a tank in 8 hours. If all three work together for 3 hours, and then pipe…
- Three pipes, A, B, and C are capable of filling a tank in 6, 8, and 12 hours, respectively. When all three pi…
About this practice question
This is a free PrajaPrep practice question for RRB NTPC Graduate. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?
- When A alone does a piece of work, he takes 25 days more than the time taken by A and B to do the work together. On the other hand, B alone takes 16 days more than the time taken by A and B to do the work together. How many days will A and B, working together, take to do the work?
- A is able to complete a task in 15 days, while B takes 20 days to finish the same task. If they collaborate and work together for 4 days, what fraction of the work will still remain?
- Pipes X, Y, and Z together can fill a tank in 8 hours. If all three work together for 3 hours, and then pipe Z is closed, the remaining tank is filled by X and Y in 10 hours. In how many hours can pipe Z alone fill the empty tank?
- Three pipes, A, B, and C are capable of filling a tank in 6, 8, and 12 hours, respectively. When all three pipes are opened together, they operate for 2 hours before pipe C is closed. How much additional time will it take to completely fill the tank after that?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Per hour: P = 1/8, Q = 1/16, R = 1/24 of the job. In 9 hours (three rounds) they print 3 × 11/48 = 33/48, leaving 15/48. Q and R together do 5/48 every 2 hours, so 15/48 takes 6 hours.