A does 60% of the work in 18 days. He then calls in B, and they together finish the remaining work in 4 days. How long would B alone take to do the whole work?
About this question
- Exam:
- SSC CHSL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A and B can do a work in 13 days and 26 days, respectively. If they work for a day alternately, starting with…
- If 8 men can do a piece of work in 14 days, the time taken by 12 men to do the same piece of work will be:
- A can paint a painting in 12 days. B can paint the same in 8 days. C can paint the same in 10 days. Find the…
- Arvind works 4 times as fast as Suresh. If Suresh can complete a work in 20 days independently, then find the…
- A pipe can fill a cistern in 8 hours. Due to a leak at the bottom, it is filled in 10 hours. In how many hour…
About this practice question
This is a free PrajaPrep practice question for SSC CHSL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A and B can do a work in 13 days and 26 days, respectively. If they work for a day alternately, starting with A, then in how many days will the work be completed?
- If 8 men can do a piece of work in 14 days, the time taken by 12 men to do the same piece of work will be:
- A can paint a painting in 12 days. B can paint the same in 8 days. C can paint the same in 10 days. Find the (approximate) number of days in which the painting can be painted by A if he is accompanied by both B and C together on alternate days and A starts painting on the first day alone.
- Arvind works 4 times as fast as Suresh. If Suresh can complete a work in 20 days independently, then find the number of days in which Arvind and Suresh can together finish the work.
- A pipe can fill a cistern in 8 hours. Due to a leak at the bottom, it is filled in 10 hours. In how many hours can the leak alone empty the full cistern?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
A’s rate is 0.6/18 = 1/30. Together they do 0.4/4 = 1/10 a day, so B’s rate is 1/10 − 1/30 = 1/15.