Tap an option below to check the answer and explanation.
A can finish a piece of work in 15 days and B in 10 days. A works alone for 5 days, and then A and B work together. The total number of days taken to finish the work is
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. After they have been open together for 2 hou…
- Two pipes together fill a tank in 6 hours. A alone fills it in 10 hours. The time, in hours, B alone would ta…
- Pipes A and B fill a tank in 6 hours and 8 hours. Pipe C empties it in 24 hours. With all three open, the tim…
- A can finish a piece of work in 10 days and B in 20 days. They work together for 4 days. If the whole work is…
- A and B can do a job in 20 and 30 days respectively. They start together, but A leaves 5 days before the work…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. After they have been open together for 2 hours, the time, in hours, still needed to fill the tank is
- Two pipes together fill a tank in 6 hours. A alone fills it in 10 hours. The time, in hours, B alone would take to fill the tank is
- Pipes A and B fill a tank in 6 hours and 8 hours. Pipe C empties it in 24 hours. With all three open, the time, in hours, taken to fill the tank is
- A can finish a piece of work in 10 days and B in 20 days. They work together for 4 days. If the whole work is 20 units, the number of units that remain is
- A and B can do a job in 20 and 30 days respectively. They start together, but A leaves 5 days before the work is completed. How many days did the work take in all?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
In 5 days A does 5/15 = 1/3, so 2/3 remains. Together they do 1/15 + 1/10 = 1/6 a day, so the rest takes 4 days, and the total is 9.