Tap an option below to check the answer and explanation.
A and B can do a job in 20 and 30 days respectively. They start together, but A leaves 5 days before the work is completed. How many days did the work take in all?
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Two pipes together fill a tank in 8 hours. One pipe takes 6 hours more than the other. The two times, in hour…
- A can finish a job in 20 days and B in 30 days. A works alone for 4 days and then B joins him. In how many mo…
- 12 men can finish a job in 30 days. In how many days will 20 men finish it?
- A and B can do a work in 8 days, B and C in 10 days, and C and A in 20 days. In how many days can C alone fin…
- A is 50% more efficient than B. If B finishes a work in 18 days, in how many days can A finish it alone?
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Two pipes together fill a tank in 8 hours. One pipe takes 6 hours more than the other. The two times, in hours, are
- A can finish a job in 20 days and B in 30 days. A works alone for 4 days and then B joins him. In how many more days will the job be finished?
- 12 men can finish a job in 30 days. In how many days will 20 men finish it?
- A and B can do a work in 8 days, B and C in 10 days, and C and A in 20 days. In how many days can C alone finish the work?
- A is 50% more efficient than B. If B finishes a work in 18 days, in how many days can A finish it alone?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Work = 60 units. In the last 5 days B does 10; the rest 50 was done together at 5/day = 10 days. Total = 15 days.