A and B can do a job in 12 and 18 days respectively. They start together, but A leaves 3 days before the work is completed. How many days did the work take in all?
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A can finish a piece of work in 6 days and B in 12 days. They work on alternate days, starting with A. The nu…
- Two pipes can fill a tank in 6 minutes and 8 minutes. A waste pipe can empty it in 12 minutes. If all three a…
- A hot pipe fills a tank in 20 minutes and a cold pipe fills it in 30 minutes. If both are opened together for…
- A and B can do a piece of work in 6 days, B and C in 8 days, and C and A in 12 days. In how many days will A,…
- A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How many days will A alone take?
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A can finish a piece of work in 6 days and B in 12 days. They work on alternate days, starting with A. The number of days they take to finish the work is
- Two pipes can fill a tank in 6 minutes and 8 minutes. A waste pipe can empty it in 12 minutes. If all three are opened, in how many minutes will the tank be full?
- A hot pipe fills a tank in 20 minutes and a cold pipe fills it in 30 minutes. If both are opened together for 5 minutes and then closed, the fraction of the tank that is full is
- A and B can do a piece of work in 6 days, B and C in 8 days, and C and A in 12 days. In how many days will A, B and C together finish the work?
- A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How many days will A alone take?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Work = 36 units. In the last 3 days B does 6; the rest 30 was done together at 5/day = 6 days. Total = 9 days.