A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How many days will A alone take?
About this question
- Exam:
- IBPS PO
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipes A and B fill a tank in 12 hours and 18 hours, and they work in alternate hours starting with A. The tim…
- Pipe A fills a tank in 20 hours and pipe B fills it in 30 hours. The time, in hours, they take together is
- 8 men finish a job in 15 days. After 5 men have worked for 8 days, 5 more men join them. The number of furthe…
- Pipe A fills a tank in 12 hours and pipe B fills it in 6 hours. The time, in hours, they take together is
- Two pipes together fill a tank in 10 hours. One pipe takes 15 hours more than the other. The two times, in ho…
About this practice question
This is a free PrajaPrep practice question for IBPS PO. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipes A and B fill a tank in 12 hours and 18 hours, and they work in alternate hours starting with A. The time, in hours, taken to fill the tank is
- Pipe A fills a tank in 20 hours and pipe B fills it in 30 hours. The time, in hours, they take together is
- 8 men finish a job in 15 days. After 5 men have worked for 8 days, 5 more men join them. The number of further days needed to finish the job is
- Pipe A fills a tank in 12 hours and pipe B fills it in 6 hours. The time, in hours, they take together is
- Two pipes together fill a tank in 10 hours. One pipe takes 15 hours more than the other. The two times, in hours, are
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Add the three pair rates: 1/12 + 1/15 + 1/20 = 12/60. That counts every person twice, so A + B + C together do half of it, 12/120 = 1/10 of the job a day. Take away B + C: 1/10 − 1/15 = 1/30, so A alone takes 30 days. Forgetting to halve gives 7 1/2 days.