A and B finish a job in 10 days, B and C in 12 days, and C and A in 15 days. How many days will A alone take?
About this question
- Exam:
- IBPS Clerk
- Topic:
- Arithmetic · Time and work
More questions on this topic
- 4 men and 6 women finish a job in 6 days, and their work rates satisfy 1 man = 2 women. The number of days th…
- A can finish a piece of work in 10 days and B in 15 days. They work on alternate days, starting with A. The n…
- A pipe can fill a tank in 10 hours. Because of a leak, it takes 15 hours to fill the tank. In how many hours…
- A can finish a piece of work in 5 days and B in 20 days. They work on alternate days, starting with A. The nu…
- A and B can do a job in 12 and 18 days respectively. They start together, but A leaves 3 days before the work…
About this practice question
This is a free PrajaPrep practice question for IBPS Clerk. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- 4 men and 6 women finish a job in 6 days, and their work rates satisfy 1 man = 2 women. The number of days that 2 men and 2 women would take is
- A can finish a piece of work in 10 days and B in 15 days. They work on alternate days, starting with A. The number of days they take to finish the work is
- A pipe can fill a tank in 10 hours. Because of a leak, it takes 15 hours to fill the tank. In how many hours would the leak empty a full tank?
- A can finish a piece of work in 5 days and B in 20 days. They work on alternate days, starting with A. The number of days they take to finish the work is
- A and B can do a job in 12 and 18 days respectively. They start together, but A leaves 3 days before the work is completed. How many days did the work take in all?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Add the three pair rates: 1/10 + 1/12 + 1/15 = 15/60. That counts every person twice, so A + B + C together do half of it, 15/120 = 1/8 of the job a day. Take away B + C: 1/8 − 1/12 = 1/24, so A alone takes 24 days. Forgetting to halve gives 6 days.