A can finish a piece of work in 20 days and B in 30 days. A works alone for 5 days, and then A and B work together. The total number of days taken to finish the work is
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipes A, B and C can fill a tank in 20, 30 and 60 hours. With all three open, the time, in hours, taken to fi…
- A can finish a piece of work in 6 days and B in 12 days. They work together for 2 days. If the whole work is…
- A can finish a piece of work in 10 days, B in 15 days and C in 30 days. They work together for 2 days. If the…
- A and B can do a work in 9 days, B and C in 12 days, and C and A in 18 days. In how many days can C alone fin…
- A can finish a piece of work in 16 days and B in 48 days. They work together for 4 days. If the whole work is…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipes A, B and C can fill a tank in 20, 30 and 60 hours. With all three open, the time, in hours, taken to fill the tank is
- A can finish a piece of work in 6 days and B in 12 days. They work together for 2 days. If the whole work is 12 units, the number of units that remain is
- A can finish a piece of work in 10 days, B in 15 days and C in 30 days. They work together for 2 days. If the whole work is 60 units, the number of units that remain is
- A and B can do a work in 9 days, B and C in 12 days, and C and A in 18 days. In how many days can C alone finish the work?
- A can finish a piece of work in 16 days and B in 48 days. They work together for 4 days. If the whole work is 48 units, the number of units that remain is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
In 5 days A does 5/20 = 1/4, so 3/4 remains. Together they do 1/20 + 1/30 = 1/12 a day, so the rest takes 9 days, and the total is 14.