Tap an option below to check the answer and explanation.
A can finish a piece of work in 16 days and B in 48 days. They work together for 4 days. If the whole work is 48 units, the number of units that remain is
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A can do a piece of work in 16 days and B in 24 days. They start together, but A leaves after 4 days. In how…
- A does 40% of a work in 8 days. At this rate, how many more days will A need to finish the remaining work?
- Two pipes can fill a cistern in 12 hours and 18 hours. Both are opened together, but after 4 hours the first…
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. The time, in hours, that they take together…
- 18 men, working 8 hours a day, finish a job in 20 days. The number of days that 24 men would take, working 6…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A can do a piece of work in 16 days and B in 24 days. They start together, but A leaves after 4 days. In how many days in all is the work finished?
- A does 40% of a work in 8 days. At this rate, how many more days will A need to finish the remaining work?
- Two pipes can fill a cistern in 12 hours and 18 hours. Both are opened together, but after 4 hours the first is closed. How many more hours will the second pipe take to fill the cistern?
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. The time, in hours, that they take together to fill the tank is
- 18 men, working 8 hours a day, finish a job in 20 days. The number of days that 24 men would take, working 6 hours a day, is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Together they do 3 + 1 = 4 units a day, so in 4 days they do 16, and 32 remain. 16 is the work already done.