A and B can do a work in 10 days, B and C in 15 days, and C and A in 18 days. In how many days can C alone finish the work?
About this question
- Exam:
- SBI PO
- Topic:
- Arithmetic · Time and work
More questions on this topic
- The efficiencies of A and B are in the ratio 3 : 2. If A alone can do a work in 10 days, in how many days can…
- Two pipes can fill a cistern in 10 hours and 15 hours. Both are opened together, but after 3 hours the first…
- Two pipes can fill a tank in 15 minutes and 20 minutes. A waste pipe can empty it in 60 minutes. If all three…
- 20 workers dig a 40 m trench in 6 days. How many workers are needed to dig a 60 m trench in 6 days?
- A can finish a piece of work in 12 days and B in 6 days. They work on alternate days, starting with A. The nu…
About this practice question
This is a free PrajaPrep practice question for SBI PO. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- The efficiencies of A and B are in the ratio 3 : 2. If A alone can do a work in 10 days, in how many days can they finish it together?
- Two pipes can fill a cistern in 10 hours and 15 hours. Both are opened together, but after 3 hours the first is closed. How many more hours will the second pipe take to fill the cistern?
- Two pipes can fill a tank in 15 minutes and 20 minutes. A waste pipe can empty it in 60 minutes. If all three are opened, in how many minutes will the tank be full?
- 20 workers dig a 40 m trench in 6 days. How many workers are needed to dig a 60 m trench in 6 days?
- A can finish a piece of work in 12 days and B in 6 days. They work on alternate days, starting with A. The number of days they take to finish the work is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Add the three pair rates: 1/10 + 1/15 + 1/18 = 20/90. That counts every person twice, so A + B + C together do half of it, 20/180 = 1/9 of the job a day. Take away A + B: 1/9 − 1/10 = 1/90, so C alone takes 90 days. Forgetting to halve gives 8 2/11 days.