Two pipes can fill a tank in 15 minutes and 20 minutes. A waste pipe can empty it in 60 minutes. If all three are opened, in how many minutes will the tank be full?
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- 20 workers dig a 40 m trench in 6 days. How many workers are needed to dig a 60 m trench in 6 days?
- A can finish a piece of work in 12 days and B in 6 days. They work on alternate days, starting with A. The nu…
- A and B can do a piece of work in 10 days, B and C in 12 days, and C and A in 15 days. In how many days will…
- If 2 men do as much work as 3 women, and 6 men finish a job in 12 days, the number of women needed to finish…
- A is three times as efficient as B. Together they finish a work in 12 days. In how many days can B alone fini…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- 20 workers dig a 40 m trench in 6 days. How many workers are needed to dig a 60 m trench in 6 days?
- A can finish a piece of work in 12 days and B in 6 days. They work on alternate days, starting with A. The number of days they take to finish the work is
- A and B can do a piece of work in 10 days, B and C in 12 days, and C and A in 15 days. In how many days will A, B and C together finish the work?
- If 2 men do as much work as 3 women, and 6 men finish a job in 12 days, the number of women needed to finish the same job in 9 days is
- A is three times as efficient as B. Together they finish a work in 12 days. In how many days can B alone finish it?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Net rate = 1/15 + 1/20 − 1/60 = 0.1 per minute; time = 10 min.