Tap an option below to check the answer and explanation.
A can finish a work in 12 days and B in 18 days. Working together, they finish it in:
About this question
- Exam:
- TSPSC Group 4
- Topic:
- Arithmetic · Time and work
More questions on this topic
- 8 men can complete a job in 15 days. How many days will 10 men take for the same job (same rate)?
- 8 men do a job in 15 days. 10 men take:
- 12 men working 8 hours a day finish a job in 10 days. How many days will 15 men working 8 hours a day take?
- A can finish a piece of work in 8 days and B in 24 days. They work together for 2 days. The number of further…
- A can finish a piece of work in 4 days and B in 12 days. They work on alternate days, starting with A. The nu…
About this practice question
This is a free PrajaPrep practice question for TSPSC Group 4. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- 8 men can complete a job in 15 days. How many days will 10 men take for the same job (same rate)?
- 8 men do a job in 15 days. 10 men take:
- 12 men working 8 hours a day finish a job in 10 days. How many days will 15 men working 8 hours a day take?
- A can finish a piece of work in 8 days and B in 24 days. They work together for 2 days. The number of further days they need, still working together, to finish what remains is
- A can finish a piece of work in 4 days and B in 12 days. They work on alternate days, starting with A. The number of days they take to finish the work is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Combined rate = 1/12 + 1/18 = 5/36; time = 36/5 = 7.2 days.