A large public-sector super-thermal power station in Telangana is at:
About this question
- Exam:
- TGPSC Group 2
- Topic:
- Economy · Telangana economy
More questions on this topic
- Hyderabad's pharma/IT image is often paired with:
- As per the 2011 Census, Telangana’s population was about 3.50 crore, making it:
- Rythu Bandhu, the 2018 scheme that Rythu Bharosa replaced in 2025, paid eligible Telangana landowners a per-a…
- Hyderabad's IT image is closely tied to:
- Telangana has how many districts and what geographical area?
About this practice question
This is a free PrajaPrep practice question for TGPSC Group 2. It belongs to Economy · Telangana economy. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Hyderabad's pharma/IT image is often paired with:
- As per the 2011 Census, Telangana’s population was about 3.50 crore, making it:
- Rythu Bandhu, the 2018 scheme that Rythu Bharosa replaced in 2025, paid eligible Telangana landowners a per-acre grant that was:
- Hyderabad's IT image is closely tied to:
- Telangana has how many districts and what geographical area?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Ramagundam NTPC in the Godavari–coal belt. Kudankulam/Tarapur are not Telangana.