A can finish a job in 18 days and B can finish it in 9 days. They do it together and are paid ₹2,700. What is A's share?
About this question
- Exam:
- Telangana SI (TSLPRB)
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A can finish a job in 24 days and B can finish it in 40 days. They do it together and are paid ₹6,400. What i…
- A does a job in 8 days, B in 24 days. Together they take:
- Hari finishes a task in 9 days and Isha in 18 days. Together they need:
- A finishes a job in 12 days, B in 18. Working together they finish in:
- 45 workers finish a job in 16 days. How many days will 18 workers take, same rate?
About this practice question
This is a free PrajaPrep practice question for Telangana SI (TSLPRB). It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A can finish a job in 24 days and B can finish it in 40 days. They do it together and are paid ₹6,400. What is A's share?
- A does a job in 8 days, B in 24 days. Together they take:
- Hari finishes a task in 9 days and Isha in 18 days. Together they need:
- A finishes a job in 12 days, B in 18. Working together they finish in:
- 45 workers finish a job in 16 days. How many days will 18 workers take, same rate?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Wages go by work done per day: 1/18 : 1/9 = 1:2. A gets ₹2,700 × 9/27 = ₹900.