Tap an option below to check the answer and explanation.
15 workers dig a 30 m trench in 10 days. How many workers are needed to dig a 50 m trench in 5 days?
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Two pipes together fill a tank in 6 hours. One pipe takes 16 hours more than the other. The faster pipe, alon…
- A and B can do a job in 10 and 15 days respectively. They start together, but A leaves 2 days before the work…
- Pipe A fills a tank in 15 hours and pipe B fills it in 10 hours. The time, in hours, they take together to fi…
- A and B can do a work in 10 days, B and C in 12 days, and C and A in 15 days. How many days will B alone take?
- 10 workers dig a 50 m trench in 8 days. How many workers are needed to dig a 80 m trench in 16 days?
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Two pipes together fill a tank in 6 hours. One pipe takes 16 hours more than the other. The faster pipe, alone, takes how many hours?
- A and B can do a job in 10 and 15 days respectively. They start together, but A leaves 2 days before the work is completed. How many days did the work take in all?
- Pipe A fills a tank in 15 hours and pipe B fills it in 10 hours. The time, in hours, they take together to fill half the tank is
- A and B can do a work in 10 days, B and C in 12 days, and C and A in 15 days. How many days will B alone take?
- 10 workers dig a 50 m trench in 8 days. How many workers are needed to dig a 80 m trench in 16 days?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
15 × 10 × 50 ÷ (30 × 5) = 50 workers.