Tap an option below to check the answer and explanation.
A can finish a job in 12 days and B can finish it in 18 days. They work together for 3 days, and then A finishes the rest alone. The further number of days that A works is
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A pipe can fill a tank in 12 hours. Because of a leak, it takes 18 hours to fill the tank. In how many hours…
- A rectangular tank measures 8 m by 5 m by 3 m. A pipe delivers 20 cubic metres of water per hour. The time, i…
- A can finish a piece of work in 8 days, B in 12 days and C in 24 days. They work together for 2 days. If the…
- Two pipes together fill a tank in 4 hours, and one takes 3 hours more than the other. The slower pipe, alone,…
- A can finish a job in 18 days and B in 36 days. A works alone for 6 days and then B joins him. In how many mo…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A pipe can fill a tank in 12 hours. Because of a leak, it takes 18 hours to fill the tank. In how many hours would the leak empty a full tank?
- A rectangular tank measures 8 m by 5 m by 3 m. A pipe delivers 20 cubic metres of water per hour. The time, in hours, taken to fill the tank is
- A can finish a piece of work in 8 days, B in 12 days and C in 24 days. They work together for 2 days. If the whole work is 24 units, the number of units that remain is
- Two pipes together fill a tank in 4 hours, and one takes 3 hours more than the other. The slower pipe, alone, takes how many hours?
- A can finish a job in 18 days and B in 36 days. A works alone for 6 days and then B joins him. In how many more days will the job be finished?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Together they do 1/12 + 1/18 = 5/36 a day, so in 3 days they do 15/36 = 5/12. The remaining 7/12 is done by A at 1/12 a day, which takes 7 days.