A and B finish a job in 12 days, B and C in 16 days, and C and A in 24 days. How many days will A alone take?
About this question
- Exam:
- RRB NTPC Graduate
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipe A fills a tank in 12 hours. After 3 hours, pipe B is also opened, and the tank is then filled in 3 more…
- If 6 men, working at the same rate, can finish a work in 10 days, how many men are needed to finish it in 4 d…
- If 2 men = 3 women = 6 children in work rate, and 4 men finish a job in 9 days, the number of days that 3 wom…
- A can do a piece of work in 12 days and B in 18 days. They start together, but A leaves after 4 days. In how…
- A can finish a job in 12 days and B in 24 days. A works alone for 3 days and then B joins him. In how many mo…
About this practice question
This is a free PrajaPrep practice question for RRB NTPC Graduate. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipe A fills a tank in 12 hours. After 3 hours, pipe B is also opened, and the tank is then filled in 3 more hours. The time, in hours, that B alone would take to fill the tank is
- If 6 men, working at the same rate, can finish a work in 10 days, how many men are needed to finish it in 4 days?
- If 2 men = 3 women = 6 children in work rate, and 4 men finish a job in 9 days, the number of days that 3 women and 6 children would take is
- A can do a piece of work in 12 days and B in 18 days. They start together, but A leaves after 4 days. In how many days in all is the work finished?
- A can finish a job in 12 days and B in 24 days. A works alone for 3 days and then B joins him. In how many more days will the job be finished?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Add the three pair rates: 1/12 + 1/16 + 1/24 = 9/48. That counts every person twice, so A + B + C together do half of it, 9/96 = 3/32 of the job a day. Take away B + C: 3/32 − 1/16 = 1/32, so A alone takes 32 days. Forgetting to halve gives 8 days.