A is twice as good a workman as B. Together they finish a work in 14 days. In how many days can A alone finish the work?
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- A can do a work in 12 days and B can do it in 18 days. What is the ratio of their efficiencies?
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. The time, in hours, they take together to fi…
- Two pipes together fill a tank in 12 hours. One pipe takes 10 hours more than the other. The faster pipe, alo…
- 16 men working 6 hours a day finish a job in 15 days. How many days will 20 men working 8 hours a day take?
- A can finish a job in 15 days and B in 30 days. A works alone for 5 days and then B joins him. In how many mo…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- A can do a work in 12 days and B can do it in 18 days. What is the ratio of their efficiencies?
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. The time, in hours, they take together to fill the tank is
- Two pipes together fill a tank in 12 hours. One pipe takes 10 hours more than the other. The faster pipe, alone, takes how many hours?
- 16 men working 6 hours a day finish a job in 15 days. How many days will 20 men working 8 hours a day take?
- A can finish a job in 15 days and B in 30 days. A works alone for 5 days and then B joins him. In how many more days will the job be finished?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Efficiency 2 : 1, so together 3 parts a day. They finish in 14 days, so total work = 42 parts. A does 2 parts a day, so A takes 21 days.