A can finish a piece of work in 10 days and B in 15 days. They work on alternate days, starting with A. If the whole work is 60 units, the number of units that remain after 4 days is
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipe A fills a tank in 12 hours and pipe B fills it in 18 hours. If the tank's capacity is taken as the LCM o…
- A and B can do a piece of work in 12 days, B and C in 16 days, and C and A in 24 days. In how many days will…
- Two pipes can fill a cistern in 8 hours and 24 hours. Both are opened together, but after 2 hours the first i…
- A pipe can fill a cistern in 6 hours, but because of a leak it takes 8 hours. The time, in hours, that the le…
- A can finish a piece of work in 12 days and B in 6 days. A works alone for 3 days, and then A and B work toge…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipe A fills a tank in 12 hours and pipe B fills it in 18 hours. If the tank's capacity is taken as the LCM of 12 and 18, the number of litres A fills in one hour is
- A and B can do a piece of work in 12 days, B and C in 16 days, and C and A in 24 days. In how many days will A, B and C together finish the work?
- Two pipes can fill a cistern in 8 hours and 24 hours. Both are opened together, but after 2 hours the first is closed. How many more hours will the second pipe take to fill the cistern?
- A pipe can fill a cistern in 6 hours, but because of a leak it takes 8 hours. The time, in hours, that the leak alone would take to empty the full cistern is
- A can finish a piece of work in 12 days and B in 6 days. A works alone for 3 days, and then A and B work together. The total number of days taken to finish the work is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
A does 6 units a day and B does 4. The four days run A, B, A, B, which is 6 + 4 + 6 + 4 = 20 units done, so 40 remain. 20 is the work already done, not the remainder.