From next month the factory will run a second shift from 2 pm to 10 pm, in addition to the existing 6 am to 2 pm shift. Overtime rates will apply only after 10 pm. Which of the following can be concluded about overtime?
About this question
- Exam:
- SSC CGL
- Topic:
- Reasoning · Analysis
More questions on this topic
- Statements: I. Heavy rain fell on the district through the night. II. Several low-lying roads in the district…
- Assertion (A): Days and nights occur on Earth. Reason (R): The Earth revolves around the Sun.
- A machine arranges the shortest remaining word to the left at each step; if two words have the same length, i…
- A machine, in one step, moves the smallest remaining odd number to the left end and the largest remaining eve…
- How many steps does the same machine take to reach its last arrangement?
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Reasoning · Analysis. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Statements: I. Heavy rain fell on the district through the night. II. Several low-lying roads in the district were under water this morning. Which of the following is correct?
- Assertion (A): Days and nights occur on Earth. Reason (R): The Earth revolves around the Sun.
- A machine arranges the shortest remaining word to the left at each step; if two words have the same length, it uses alphabetical order, and the other words keep their old order. Input: mango table ant peach ice. Step I is
- A machine, in one step, moves the smallest remaining odd number to the left end and the largest remaining even number to the right end. Words keep their relative order. Input: 41 park 18 lamp 27 door 36. Step I is
- How many steps does the same machine take to reach its last arrangement?
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Overtime rates apply only after 10 pm, so work ending at 10 pm is not overtime on these rules. The second shift itself runs to 10 pm, and the passage does not ban all later work or start overtime at 6 am.