A can finish a piece of work in 20 days and B in 30 days. They work together for 5 days. If the whole work is 60 units, the number of units that remain is
About this question
- Exam:
- SSC CGL
- Topic:
- Arithmetic · Time and work
More questions on this topic
- Pipe A fills a tank in 8 hours and pipe B empties it in 12 hours. If both are opened together, the time, in h…
- 10 men can finish a job in 12 days. In how many days will 8 men finish it?
- 24 men working 5 hours a day finish a job in 12 days. How many days will 18 men working 8 hours a day take?
- A can do a piece of work in 10 days and B in 15 days. They start together, but A leaves after 3 days. In how…
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. A works alone for 2 hours, then A and B work…
About this practice question
This is a free PrajaPrep practice question for SSC CGL. It belongs to Arithmetic · Time and work. Pick an option above to see whether you are right, then read a short explanation. The page is for students preparing for Telangana and All-India government exams in Telugu, Urdu and English. PrajaPrep is not an official board app, and this question is not a substitute for the official notification or question paper. After you try it, you can sign in free and continue in the app with daily practice, lessons and mocks. Related questions from the same topic are listed here so you can keep practising from this chapter.
Related questions
- Pipe A fills a tank in 8 hours and pipe B empties it in 12 hours. If both are opened together, the time, in hours, taken to fill the tank is
- 10 men can finish a job in 12 days. In how many days will 8 men finish it?
- 24 men working 5 hours a day finish a job in 12 days. How many days will 18 men working 8 hours a day take?
- A can do a piece of work in 10 days and B in 15 days. They start together, but A leaves after 3 days. In how many days in all is the work finished?
- Pipe A fills a tank in 10 hours and pipe B fills it in 15 hours. A works alone for 2 hours, then A and B work together for 3 hours, then B alone finishes what remains. The total time taken is
Answer and explanation
If you want to check after trying the question, the short explanation is here.
Together they do 3 + 2 = 5 units a day, so in 5 days they do 25, and 35 remain. 25 is the work already done.