Arithmetic · 8 min

Finding one person's time from the times of pairs

Lesson

Here is a worked case. A and B take 10 days, B and C take 12, C and A take 15. Then 1/10 + 1/12 + 1/15 = 1/4. Half of that is 1/8, so the three together finish the job in 8 days. A's one-day work is 1/8 − 1/12 = 1/24, so A alone needs 24 days. C's one-day work is 1/8 − 1/10 = 1/40, so C needs 40 days. The usual trap is to treat the pair time as one person's time, or to forget to halve the sum of the three pair rates.

Remember these

If A and B together finish a job in x days, B and C in y days, and C and A in z days, then the three pairs together have done the work twice over, because each person appears in two pairs. So 2(A + B + C) in one day's work equals 1/x + 1/y + 1/z. One day's work of all three is half of that sum, and A alone is that total minus B and C's combined rate.

Why the paper asks this

This pair-sum pattern is a regular time-and-work question in SSC, RRB, banking and NDA papers.

Worked example

A+B = 10 days, B+C = 12, C+A = 15. Sum of rates = 1/4, so all three do 1/8 a day and finish in 8 days. A alone: 1/8 − 1/12 = 1/24, so 24 days.

Common trap

Taking the pair time as one person's time, or forgetting to halve the sum of the three pair rates.

Source: NCERT mathematics and the SSC, RRB, TSLPRB and banking quantitative syllabi; written in our own words