Time and work when people leave or join midway

Lesson

Say A can finish a job in 12 days and B in 18 days. Instead of fractions, call the job 36 units, the LCM of 12 and 18. A does 3 units a day and B does 2. Working together they do 5 units a day. Thinking in units keeps every later step to simple multiplication and subtraction.

Now let them start together, and after 4 days A leaves. In those 4 days they finish 4 × 5 = 20 units, so 16 units remain. B alone does 2 a day, so B needs 8 more days. The job takes 4 + 8 = 12 days in all. The same phase-by-phase thinking handles a worker who joins late: count what the early workers finished, then share what is left at the new combined rate.

A common twist says A leaves a few days before the job ends. Work backwards then. In the last few days only B works, so subtract B's share of those days from the total, and the rest was done by both together. Write each phase on its own line and the answer appears without guessing.

Remember these

Take the total work as the LCM of the given days; each person's daily work is then a whole number.

Split the job into phases. Work done in each phase = (combined daily rate) × (days in that phase), and the phases add up to the total.

Why the paper asks this

Leaving-and-joining sums are the time-and-work variety most often set in SSC CGL and CHSL.

Worked example

A 10 days, B 15 days, together 3 days then A leaves: 30 units, 3 × 5 = 15 done, B needs 15 ÷ 2 = 7.5 more days.

Common trap

Adding the days of different phases without checking how much work each phase actually did.

Source: NCERT mathematics and the SSC, RRB, TSLPRB and banking quantitative syllabi; written in our own words

Sign up to continue learning

This lesson is free to read. Sign up free to open the next lesson in the app, keep your progress, and practise questions on this topic.

Sign up to continue learning